How Long Does a Building Consent Take in Palmerston North and the Manawatū?

The short answer: the law gives council 20 working days to decide a building consent. In practice, on the homes we have designed and lodged in Palmerston North and the Manawatū, it takes a little longer, and the design work before lodgement takes longer again. Here are our own figures, from our job records, and what you can do to keep your consent moving.
What the law says
Under the Building Act 2004 (section 48), a building consent authority has 20 working days from receiving your application to grant or refuse it. Two things stretch that in real life:
Requests for further information (RFIs). If council asks a question about your application, the 20-day clock stops until they get the answer. MBIE calls this "stopping the clock".
Working days, not calendar days. Weekends and public holidays don't count, and nor does anything from 20 December to 10 January. A consent lodged in mid-December won't really get going until mid-January.
How long consents actually take: our figures
We track every consent we lodge on the same clock council works to: working days only, with the clock paused while council waits on answers to a request for information. So these are true processing times under the Act, not elapsed time. The averages by council, as at November 2026:
Palmerston North City Council: 22.8 working days on the statutory clock (77 consents). 55% drew at least one request for information.
Manawatū District Council: 25.2 working days (54 consents). 57% drew at least one request for information.
Horowhenua District Council: 21.8 working days (8 consents).
Both Palmerston North and the Manawatū are running past the 20 working days the Act allows, on average, even with RFI time taken out. Across 152 consents with complete dates, the average is 28.6 working days on the clock. Add weekends, holidays and any time spent answering RFIs, and six to eight weeks from lodgement is a realistic expectation. That overall figure includes a handful of long-running and out-of-district jobs, so the council figures above are the better guide for a house in the region.
Engineering adds about two weeks. Consents that needed engineering took 33.6 working days on average, against 23.3 for those that didn't, a difference of about 10 working days. Foundations on poor ground, large openings, steel beams and retaining walls are the usual reasons a house needs an engineer.
The whole timeline: from first meeting to consent
Council's time is only part of it. On our jobs, the average time from booking the concept design to lodging the consent is about four months (113 days over the last six months). Roughly:
Concept design: about seven weeks over the last six months, most of it working through options with you.
Consent drawings: about three weeks to prepare the full working drawings, specification and calculations.
Council processing: five to eight weeks in real time, as above.
So for a new home, allow around five to six months from first meeting to a consent in hand, longer if engineering, a geotechnical report or a resource consent is needed.
How to keep your consent moving
Order the geotech report early. If your section needs one, it is often the longest wait before lodgement.
Settle the design before the consent drawings start. Changes during the consent stage cost time twice: once to redraw, and again if council has already started.
Lodge complete. A full set of drawings, specification, calculations and supporting documents gives council fewer reasons to stop the clock.
Answer RFIs quickly. We handle council's questions as your agent, so the clock restarts as soon as we can respond.
Watch the Christmas break. Lodging in late November or early December can mean waiting until mid-January.
Want a timeline for your project?
Every project is different, so we'll give you a realistic programme at your free first meeting, along with a fixed fee. Call 0800 639 346 or email Info@newdimension.nz.
Figures are averages from New Dimension's own job records as at November 2026 and will vary by project and council workload. They are not a guarantee of any council's processing time.
About the author
Mike Hansen is the director and principal designer at New Dimension Architecture in Feilding. He is a Licensed Building Practitioner (Design 2) and an ADNZ Certified Professional Member, and has been designing homes across Palmerston North and the Manawatū for 20 years. Meet the team.